Bonjour,

j'ai trouvé fonctions qui calculte nombre de jours total entre deux dates sans compter weekend

<?php
//The function returns the no. of business days between two dates and it skeeps the holidays
function getWorkingDays($startDate,$endDate,$holidays){
//The total number of days between the two dates. We compute the no. of seconds and divide it to 60*60*24
//We add one to inlude both dates in the interval.
$days = (strtotime($endDate) - strtotime($startDate)) / 86400 + 1;

$no_full_weeks = floor($days / 7);
$no_remaining_days = fmod($days, 7);

//It will return 1 if it's Monday,.. ,7 for Sunday
$the_first_day_of_week = date("N",strtotime($startDate));
$the_last_day_of_week = date("N",strtotime($endDate));

//---->The two can be equal in leap years when february has 29 days, the equal sign is added here
//In the first case the whole interval is within a week, in the second case the interval falls in two weeks.
if ($the_first_day_of_week <= $the_last_day_of_week){
if ($the_first_day_of_week <= 6 && 6 <= $the_last_day_of_week) $no_remaining_days--;
if ($the_first_day_of_week <= 7 && 7 <= $the_last_day_of_week) $no_remaining_days--;
}
else{
if ($the_first_day_of_week <= 6) $no_remaining_days--;
//In the case when the interval falls in two weeks, there will be a Sunday for sure
$no_remaining_days--;
}

//The no. of business days is: (number of weeks between the two dates) * (5 working days) + the remainder
//---->february in none leap years gave a remainder of 0 but still calculated weekends between first and last day, this is one way to fix it
$workingDays = $no_full_weeks * 5;
if ($no_remaining_days > 0 )
{
$workingDays += $no_remaining_days;
}

//We subtract the holidays
foreach($holidays as $holiday){
$time_stamp=strtotime($holiday);
//If the holiday doesn't fall in weekend
if (strtotime($startDate) <= $time_stamp && $time_stamp <= strtotime($endDate) && date("N",$time_stamp) != 6 && date("N",$time_stamp) != 7)
$workingDays--;
}

return $workingDays;
}
?>

et si je met

<?php
$holidays=array("2006-12-25","2006-12-26","2007-01-01");

echo getWorkingDays("2006-12-22","2007-01-06",$holidays)
?>

j'aurais resultat 8
mais comment on fait pour donner beaucoup de dates a cete fonction et avoir resultat total
par exemple si je done deux foix ces deux dates j'aurais résultat 16
j'ai essayé de déclarer array dans fonction mais toujours erreur:

<?php
Parse error: parse error, unexpected T_VARIABLE, expecting ')'
?>Configuration: Windows 2000
Internet Explorer 6.0


Tiller
août 08
Suivant
REPONSES
Tiller
août 08
tigre198
août 08
Tiller
août 08
tigre198
août 08
Version Web
Réalisé par RedShift
no save